The external works to this purpose-built mansion block in Maida Vale are now coming to an end.
This has been a complex project to execute both technically & logistically, but it was a great project to be involved with and we are delighted with the outcome.
The works undertaken to this property included the following:
- Demolished and rebuilt the retaining wall between blocks 4 & 5
- Carried out entrance bridge(s) re-construction & repairs to 5no entrances. (2no were demolished and completely re-built, 3 No were repaired in situ in accordance with the engineer’s requirements) – whilst maintaining the ingress & egress into the building for 105 flats
- Renewal of concrete slabs to a number or vaults, then introduce waterproofing to all vaults (including entrances)
- Mechanical & Electrical works (including liaison with EDF & UKPN to carry out upgrades with scheduled power outages)
- Vault Door replacements & repairs
- London Mosaic Tiling to 5no entrances (& 2no basement staircases)
- Installation of new Granite thresholds to all entrances
- Metal works repairs
- Extensive Masonry works, including fully repointing 5no entrances
- External decoration works to all ground floor and low-level areas.