Demelza

Collins are incredibly proud to have supported Demelza throughout 2024, raising donations through a number of fundraising events, along with sponsoring and supporting Demelza events across the year. It has been an honour to support this incredible local children’s charity to assist them in being able to continue providing the endless services, care & support…

Collins Annual Training Day

Our company annual training day was held at the end of December. The day’s objective was to inform staff of any updated Health & Safety, Site Management and Company Policies. The training day also gives us an opportunity to come together as a team and discuss any concerns, suggestions for improvements or share positive experiences.

Chiltern Court

This colossal scaffold is complete and handed over, the works onsite are now well underway. The façade cleaning has been completed and we are now working closely with the client’s appointed engineers, to identify the extent of the repairs required and the appropriate methods to restore the building, back to its former glory. We look…

Royal Westminster Lodge

The works are coming to an end here at Royal Westminster Lodge, this weekend we were onsite carrying out the last few items, this included introducing firestopping to voids within the substrate, then applying a cementitious spray system to encapsulate. We look forward to sharing the completed project shortly.

Jenner Court

This Grade II Listed building’ located in North West London, is currently undergoing an extensive refurbishment to the external facades. The following works are progressing well onsite: Doff Clean is now complete Timber repairs are being undertaken Schedules agreed and masonry works underway. Preparing for external decoration   Look out for further project updates as…

The Giving Tree Returns to Collins

Following the huge success of last year’s Giving Tree, it seemed like an obvious choice to continue our support for the ‘Salvation Army Christmas Present Appeal’ A representative of the Salvation Army had shared with us, that in previous years they hadn’t had enough donations to fulfil all families they support, but with the support…

59-61 Cadogan Gardens

The external repairs and redecorations project to this period property located in the heart of Chelsea, is progressing well. Works to date: Timber repairs to the windows are almost complete Roof tile repairs and the new liquid roofing are making good progress The external redecorations are ongoing and will be completed in early January This…

34-37 Sloane Square

Works are progressing well onsite; We are continuing the installation of the ceiling sub grid in preparation for the new MF ceilings, introducing fire lining to the structural steel columns and beams, installing new drainage runs in the basement and laying the blockwork walls to divide the units. Look out for more updates shortly.

Bedford Riverside

The strip out and reinstatement works are almost complete to this riverside restaurant located in Bedford. Collins have been refurbishing this fire damaged property, which will become a Tapas restaurant. Look out for completed photos coming soon.

96 Queensway

At 96 Queensway, the new roof is now complete, and the temporary roof can be removed. We are progressing well with reconstructing the new floors in accordance with the engineer’s design, ready for the M&E and fit out works to begin. We shall continue to share updates as works progress.