Hyde Park Gardens

Scaffold has been dismantled to 1st floor balcony level on the garden facing elevation following completion of the structural works to the chimney stack. We are finishing the last asphalt balcony replacements, then scaffold can be removed for the low-level works to commence. We have received planning consent to carry out the terrace waterproofing upgrade…

Lewisham Fire Station

The scaffold erection at Lewisham Fire Station is progressing well. Once the scaffold is fully erected, our works to this 59-year-old fire station can commence. We will be carrying out a full replacement of the existing roof coverings to 14no roofs. The new roofs will feature liquid-applied coverings and upgraded insulation, installed in line with…

Bickenhall Mansions

Despite the recent wet weather, our 74-week external restoration project has continued on site. Our team made the most of today’s sunshine after six weeks of rain. The project involves repair and maintenance of the street-facing facades on Bickenhall Street, Gloucester Place, and the two end flanks on Baker Street, as well as the associated…

Project Complete

Our works to this mid terraced Victorian House located in the heart of Kennington are now complete. This project included the following; Roofing repairs & sectional replacement Doff cleaning to all elevations Extensive Masonry works – including 100% repointing to both elevations Overhaul of timber windows & associated repairs Strip out & install new kitchen &…

55 Leroy Street

Works to this 19th Century three-storey commercial property in Bermondsey are now complete. Collins were appointed to carry out the general upgrade works to interior spaces from the 1st floor to the Roof. Internally our works included – Door replacements New heating and cooling installations Lighting adaptions Acoustic and fire rating upgrades Our exterior works…

Celebrating a Well-Earned Promotion

We are delighted to announce the promotion of Tom, who has progressed from Assistant to Contracts Manager. This is a fantastic achievement and a true testament to Tom’s hard work, commitment, and contribution to the business. A well-deserved next step in his career.  To mark the occasion, we treated Tom with a game of golf…

Bedford Riverside

Collins have returned to Bedford Riverside this week to carry out the end of defects inspection, and associated M&E servicing works in accordance with the client’s requirements following the refurbishment that took place a year ago, after a fire caused extensive damage requiring the unit to be fully stripped back, and reinstated ready for a…

Coppersmead

The end of defects for the internal and external refurbishment works at Coppersmead, has now successfully concluded. We are pleased with how well the building continues to look following completion of the works 12 months ago. Our works to this project included: Repairs and redecoration of all previously painted external surfaces Internal repairs and redecorations…

190-192 Sloane Street

Collins have been appointed by MFG C/o Cadogan Estates to carry out the Repair & Redecoration works to the external staircase & roofs, to this iconic property known as the ‘Sekers Building’ originally built in 1965 for the fabric company ‘Sekers Silks’. This Grade II listed building is now the home to numerous commercial units…

National Apprenticeship Week

Collins are proud to support and celebrate National Apprenticeship Week; we recognise the vital role that apprentices play in strengthening our workforce and shaping the future of the industry. We believe in investing in our apprentices and building a skilled workforce for the future. From on-site learning and mentoring to formal training and qualifications, our…