65 Holland Park

We are delighted to have commenced work this week on this Grade II listed Residential block, located in Holland Park. Our works on to the property will include the following; Externally: Full access scaffolding to all elevations Extensive masonry repairs including, rendering, repointing, helifix repairs, brick replacements etc Overhauling windows including repair care & replacement…

2-8 Hyde Park Gardens

Works are progressing well onsite here at 2-8 Hyde Park Gardens. The isolated roof repairs have been completed, and we are handing over the front elevation upper scaffold lifts today, to start the dismantling process, and enable the liquid waterproofing works to the box gutters to be undertaken. On the garden facing elevation, we have…

6 St Mary’s Walk

Works are progressing well to this mid terraced Victorian House located on the south side of St Mary’s Walk in the heart of Kennington. We have been appointed to undertake the following works; Roofing repairs & sectional replacement Doff cleaning to all elevations Extensive Masonry works – including 100% repointing to both elevations Overhaul of timber…

Royal Ocean Racing Club

Collins were delighted to return to the Royal Ocean Racing Club to carry out internal upgrades and maintenance works. The Royal Ocean Racing Club has occupied this Grade II Listed Georgian Townhouse on St. James’s Place, since Christmas Day in 1941. The headquarters offer members a ‘home from home’ to enjoy elegant en-suite accommodation, an…

Albemarle

The external refurbishment works are now underway to this high-end residential building in Wimbledon, which consists of 42 apartments. Our works here will include; Masonry restorations Balcony repairs Timber and Crittall Window repairs Fascia and Gutter replacements Roofing repairs including overlaying liquid roofs Complete external redecorations to all previously painted surfaces. Internally, our works will…

Hill House Apartments

We have just begun the internal refurbishment to 5nr flats within this block in Pentonville Road, Kings Cross. Following an internal water leak, as part of an insurance claim our works will include; Removal of tenants fixtures and fittings Removal of internal floor, ceiling and wall finishes to enable the drying out process Treat all internal…

23-26 Great James Street

Our works to the main façade of this property are nearing completion; the building has benefited from a thorough DOFF Clean and extensive Masonry and Timber Repairs. At present we are applying finishing coats to all previously painted surfaces ready for scaffold to be dismantled. As part of our works, we have been tasked to…

New Cross Fire Station

Works are progressing well at New Cross Fire Station with the scaffolding now erect. The specialist brick and stone cleaning is almost complete allowing the timber window repairs to commence. This project has been registered for the Repair Care warranty whereby a rep will attend site during progress to inspect and sign-off the quality of…

Russell Court

Works are nearing completion at Russell Court, as we work down the building, we have now handed over levels 9-4, we are snagging on levels 2-4 and are currently picking up the finishing works including installation of the bespoke carpet to ground and first floor levels. The upgrade works within Entrance A are progressing well and is…

Kent Hills, Milton Keynes

https://www.collins-contractors.co.uk/wp-content/uploads/2025/09/Untitled-design-14-1.mp4 Our certified Drone Pilot is on site today conducting a comprehensive survey of the roof. This assessment is being carried out as part of our investigation into the cause of recent water ingress affecting the building. Look out for updates coming soon.