Works are progressing well onsite at Crawley. The strip out works have been completed, our temporary propping design has been approved, and the supporting scaffold with associated steel needles have been installed, ready for the removal of the supporting dividing wall between the units.
The steels are in place and ready to be installed in accordance with the engineers design.
We look forward to sharing updates as further works develop onsite.